Res 163-2007 11/6/2007 RESOLUTION NO. 163-2007
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WICHITA
FALLS, TEXAS, TO AWARD BID AND CONTRACT FOR THE
SECONDARY RESERVOIR CHLORINE DIOXIDE FACILITY
IMPROVEMENTS PROJECT CWF07-550424; FINDING AND
DETERMINING THAT THE MEETING AT WHICH THIS RESOLUTION
WAS PASSED WAS OPEN TO THE PUBLIC AS REQUIRED BY LAW.
WHEREAS, the City of Wichita Falls has advertised for bids for the Secondary
Reservoir Chlorine Dioxide Facility Improvements Project; and
WHEREAS, it is found that the lowest, responsible bidder is Adams Construction
who made a lump sum bid with an estimated total of $259,372.00.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
SECTION 1. Said lump sum bid of Adams Construction with an estimated total of
$259,372.00 is hereby accepted, and the City Manager is authorized to execute a
contract for the City with said Contractor for the construction of such project.
SECTION 2. It is hereby officially found and determined that the meeting at
which this resolution was passed was open to the public as required by law.
PASSED AND APPROVED this the 6th day of November, 2007.
�
MAYOR
ATTEST:
�
Clerk