Res 126-2017 9/19/2017
Resolution No. _126-2017_
Resolution authorizing the City Manager to Approve Change Order
No. 1 for the 2016 Kemp Monroe Drainage Project Phase I in the
amount of $209,970.00
City of Wichita Falls entered a unit price contract with Wilson Contracting with
the estimated total cost of $3,992,634.50; and,
WHEREAS, Change Order No. 1 will increase the contract by $209,970.00 for a
revised cost of $4,202,604.50.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
The City Manager is authorized to execute Change Order No. 1 for the 2016
Kemp Monroe Drainage Project Phase I in the amount of $209,970.00.
PASSED AND APPROVED this the 19th day of September, 2017.
______________________________
M A Y O R
ATTEST:
____________________
City Clerk