Res 013-2003 2/18/2003RESOLUTION NO. V3
RESOLUTION TO AWARD BID AND CONTRACT FOR THE WOOD
MEMORIAL PARK RETAINING WALL PROJECT; FINDING AND
DETERMINING THAT THE MEETING AT WHICH THIS RESOLUTION
WAS PASSED WAS OPEN TO THE PUBLIC AS REQUIRED BY LAW.
WHEREAS, the City of Wichita Falls has advertised for bids for the construction
of the Wood Memorial Park Retaining Wall Project; and
WHEREAS, it is found that the lowest, responsible bidder is A & A Construction
Co. who made a unit price bid with an estimated total of $38,139.00.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
SECTION 1 . Said unit price bid of A & A Construction Co., with an estimated
total of $38,139.00 is hereby accepted, and the City Manager is authorized to execute a
contract for the City with said Contractor for the construction of such project.
SECTION 2 . It is hereby officially found and determined that the meeting at
which this resolution was passed was open to the public as required by law.
PASSED AND APPROVED this the 18th day of February, 2003.
ATTEST:
City Clerk