Res 164-2003 12/2/2003RESOLUTION NO. I L4 - DL'C>3
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WICHITA
FALLS, TEXAS, ACCEPTING THE MPEC COLISEUM GENERAL
CONSTRUCTION PROJECT AND AUTHORIZING FINAL PAYMENT TO
ELECTRA CONSTRUCTION COMPANY; FINDING AND DETERMINING
THAT THE MEETING AT WHICH THIS RESOLUTION WAS PASSED
WAS OPEN TO THE PUBLIC AS REQUIRED BY LAW.
WHEREAS, on May 5, 2001, the City entered into a construction contract with
Electra Construction Company, Incorporated for the MPEC Coliseum General
Construction Project in the amount of $17,870,186.11; and
WHEREAS, change orders in the amount of $253,819.91 were approved for this
contract, much of which was due to the addition of the ice plant building that was not
originally in the contract; and
WHEREAS, the total cost for this contract was $18,124,006.02, of which
$18,114,763.52 has been paid to the contractor, leaving a remaining balance of
$9,242,.50; and
WHEREAS, the work has been completed satisfactorily and found to be
acceptable to the City and the MPEC Board of Directors.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
SEC TION 1. The MPEC Coliseum General Construction Project is hereby
accepted, and the City is authorized to make final payment to the contractor.
SECTION 2 . It is hereby officially found and determined that the meeting at
which this resolution was passed was open to the public as required by law.
PASSED AND APPROVED this the 2nd day of December, 2003.
MAYOR
ATTEST:
1
City Clerk