Res 085-2003 7/15/2003RESOLUTION NO. '25
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WICHITA
FALLS, TEXAS, AWARDING BID AND CONTRACT FOR THE 2003
WATER BUDGET UTILITIES IMPROVEMENT PROJECT (BUIP) CWF
03- 550 -04; FINDING AND DETERMINING THAT THE MEETING AT
WHICH THIS RESOLUTION WAS PASSED WAS OPEN TO THE
PUBLIC AS REQUIRED BY LAW.
WHEREAS, the City of Wichita Falls has advertised for bids for the construction
of the 2003 Water Budget Utilities Improvement Project (BUIP) CWF 03- 550 -04; and
WHEREAS, it is found that the lowest, responsible bidder is Bowles Construction
Co., who made a unit price bid with an estimated total of $449,980.40.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
SECTI _1. Said unit price bid of Bowles Construction Co. with an estimated
total of $449,980.40 is hereby accepted, and the City Manager is authorized to execute
a contract for the City with said Contractor for the construction of the 2003 Water
Budget Utilities Improvement Project (BUIP) CWF 03- 550 -04.
SECTION 2 . It is hereby officially found and determined that the meeting at
which this resolution was passed was open to the public as required by law.
PASSED AND APPROVED this the 15th day of July, 2003.
M MAYOR
ATTEST: