Res 049-2004 4/6/2004RESOLUTION NO.
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WICHITA
FALLS, TEXAS, TO APPROVE CHANGE ORDER NO. 1 TO THE FAITH
VILLAGE DRAINAGE IMPROVEMENT PROJECT, PHASE 1 (CWF03-
552-03) IN THE AMOUNT OF $51,900.00 AND 30 CALENDAR DAYS,
FINDING AND DETERMINING THAT THE MEETING AT WHICH THIS
RESOLUTION WAS PASSED WAS OPEN TO THE PUBLIC AS
REQUIRED BY LAW.
WHEREAS, the City of Wichita Falls entered a unit price contract with Earth
Builders, Inc. with the estimated total cost of $2,376,500.00; and
WHEREAS, Change Order No. 1 would add $51,900.00 to the contract for a
revised cost of $2,428.400, and
WHEREAS, the City staff has reviewed all aspects of this change order and feels
that it is in the City's best interest to approve.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT
SECTI 1 . Change Order No. 1 for the Faith Village Drainage Improvement
Project, Phase 1 (CWF03- 552 -03) is hereby approved and the City Manager is
authorized to make amendments to this contract.
SECTI 2. It is hereby officially found and determined that the meeting at
which this resolution was passed was open to the public as required by law.
PASSED AND APPROVED this the 6th day of April, 2004.