Res 080-2005 6/7/2005RESOLUTION NO. 4 9Q'o6C�
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WICHITA
FALLS, TEXAS, TO ACCEPT THE 2004 WATER BUDGET UTILITY
IMPROVEMENT PROJECT (BUIP) CWF04- 550 -12 AND AUTHORIZE
FINAL PAYMENT TO WPW UTILITY CONSTRUCTION CO., INC.;
FINDING AND DETERMINING THAT THE MEETING AT WHICH THIS
RESOLUTION WAS PASSED WAS OPEN TO THE PUBLIC AS
REQUIRED BY LAW.
WHEREAS, the City of Wichita Falls entered a unit price contract with WPW
Utility Construction Co., Inc., with the estimated total cost of $196,877.00; and
WHEREAS, the actual work was completed at a total cost of $233,755.25,
including an elective change order of $34,574.00, of which $222,067.49 has been
previously paid to the contractor, leaving an amount due of $11,687.76; and
WHEREAS, the City staff has inspected the work and found it to be acceptable.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
SECTION 1 . The 2004 Water Budget Utility Improvement Project (BUIP),
CWF04- 550 -12 is hereby accepted, and the City Manager is authorized to make final
payment to the contractor.
S ECTION 2 . It is hereby officially found and determined that the meeting at
which this resolution was passed was open to the public as required by law.
PASSED AND APPROVED this the 7th day of June, 2005.
ATTEST:
MAYOR
City Clerk