Res 072-2016 7/5/2016 Resolution No. __72-2016__ Resolution approving Change Order No. 1 for the Taxiway C Reconstruction Project at Wichita Falls Regional Airport to Garver, LLC in an amount of $197,250 WHEREAS, the City of Wichita Falls entered into a contract with Garver LLC, with an estimated total cost of $379,952; and, WHEREAS, the City of Wichita Falls will incur additional project management expenses because of extensions to the project completion deadline ; and, WHEREAS, the City of Wichita Falls shall assess liquidate d damages to Mitchell Enterprises LLC, as a result of these project delays; and, WHEREAS, liquidated damages shall be used to offset the additional project management costs identified in Change Order No. 1 in the amount of $197,250; and, WHEREAS, the amended contract amount with Garver LLC shall be $577,202 ; and, WHEREAS, City staff has reviewed all aspects of this change order and believes that it is in the City’s best interest to approve. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: Change Order No. 1 for the Reconstruction of Taxiway C Project at Wichita Falls Regional Airport (AIP No. 3-48-0346-16) is hereby approved, and the City Manager is authorized to make amendments to this contract with Garver, LLC, with changes thereto in a form approved by the City Attorney, in an estimated amount of $197,250. PASSED AND APPROVED this the 5th day of July, 2016. ______________________________ M A Y O R ATTEST: ____________________ City Clerk CITY OF WICHITA FALLS, TEXAS CHANGE ORDER NO.:1 CONTRACT CHANGE ORDER FORM 7-Jul-16 197,250.00$ PROJECT/CONTRACT: TO:___Garver______, this Change Order, after approval by the Owner, will be your (Contractor) authority to make the following changes in the work under your contract: Decrease Increase Total Change in Contract in Contract in Contract -$ 197,250.00$ 197,250.00$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 197,250.00$ 197,250.00$ 379,952.00$ 197,250.00$ -$ 577,202.00$ The completion time under your contract will be extended by __200__ days because of this change order making the revised completion date _November 15, 2016_. Approved By Owner:Accepted By Contractor:Recommended By Arch/Eng: (if applicable) By:______________________By:______________________By:_____________________ Title:_____________________Title:_____________________Title:____________________ Date:_____________________Date:_____________________Date:____________________ engineering expenses until the completion of the project 2. DATE: 1. With Mitchell Enterprises being in Liquidated Damages on the Taxi- way C, project, Garver will incur testing, project representation, and Description of Changes Engineering Services for Taxiway C Project AMOUNT OF CHANGE: TOTAL AMOUNT OF ORIGINAL CONTRACT: 3. 4. TOTAL AMOUNT OF THIS CHANGE ORDER: TOTAL AMOUNT OF PREVIOUS CHANGE ORDERS: 5. CONTRACT AMOUNT TO DATE: 6.