Res 030-2016 3/15/2016Resolution No. _30-2016_
Resolution to approve Change Order No. 1 for the 2015 CDBG Waterline
Replacement Project for a Deduct of $27,765.70
WHEREAS, the City of Wichita Falls entered a unit price contract with Bowles
Construction Co. with the estimated total cost of $253,957.00; and,
WHEREAS, Change Order No. 1 will reduce the contract $27,765.70 for a
revised cost of $226,191.30.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
The City Manager is authorized to execute Change Order No. 1 for the 2015
CDBG Waterline Rehabilitation Project in the amount of $27,765.70,
PASSED AND APPROVED this the 15th day of March, 2016.
______________________________
M A Y O R
ATTEST:
____________________
City Clerk