Min 10/29/1990 567
Wichita Falls, Texas
Memorial Auditorium Building
October 29, 1990
Item 1
The City Council of the City of Wichita Falls, Texas,
met in called session on the above date in the Council Room
of the Memorial Auditorium Building at 8: 30 o'clock a.m. ,
with the following members present.
Michael Lam Mayor
David Farabee -
Charles Thomas -
Angus Thompson - Councilors
Paul Hughes -
J. W. Martin -
Don Kirkham -
Jim Berzina City Manager
Gregory D. Humbach City Attorney
Wilma J. Thomas City Clerk
Item 2
Mayor Lam noted that the purpose of this meeting is to
consider some decisions on Phase III of Holliday Creek
project.
The meeting recessed into the Council Conference Room.
Mr. Bonnett brought the Council up to date on past
events surrounding these discussions. He stated that the
dam elevation of 993 feet is satisfactory, and meets
requirements of the Dam Safety Commission. It has also been
approved by the Texas Water Commission. The Corps of
Engineers want it to be at an elevation of 996 feet. He
noted the presence of Congressman Sarpalius, stating he
appreciated the congressional help. He noted a memorandum
of agreement which had been signed by the City Manager and
Corps of Engineers. He addressed concerns about the bid
received in the amount of 3 . 8 million. The Corps estimate
is now 2. 8 million. The City has expressed that they were
flexible, and were willing to go the government ' s estimated
cost of 2. 8 million. This offer has been on the table for
three weeks. The decision of the Corps has been appealed to
the Secretary of the Army. They are very sincerely trying
to find a middle ground. Mr. Bonnett addressed questions
concerning the distance from Southwest Parkway if the dam
were 993 or 996 feet high. No residences will be affected,
but mentioned apartment buildings on Lyons Circle. Property
has been purchased to the dam height of 996 feet. He stated
the Corps has never agreed to the 993 foot dam. The cost of
$2,340,000 was twenty-five percent above the 993 foot
height.
Councilor Thomas noted that this is the first project
we have had through the Corps of Engineers to get back some
of our tax money. It was explained that when they met in
Washington, the City made it clear they were not there to
argue the height of the dam, but the money. It is unclear
why this was not taken into consideration three years ago
instead of waiting until now. It was noted that 996 is an
elevation that the Corps of Engineers designs to.
Colonel Lee Smith, of the Corps of Engineers, arrived.
Mayor Lam pointed out that the City of Wichita Falls is very
pleased with this project to date, stating it is a classic
example of the City and the Corps working together to
relieve a serious problem of flooding for the City. The
City wants to see this project completed, and are willing to
move forward to completion.
568
Colonel Smith stated they are dedicated to serving the
citizens here in Wichita Falls, and throughout the United
States. They are a problem solving agency. In cases such
as this, they are asked to come in when a local project is
identified. If the problem falls within their area of
expertise, the Congress is asked to study and fund it. It
is also up to the local sponsor to decide if twenty-five
percent of the cost can be paid by the local people. He
noted that this project is not a Corps project but a City of
Wichita Falls project. They have no problem with coming up
with their share of the 48 million project. He explained
that he is the one who has to make the decision on what to
do with the bids he received.
Colonel Smith reviewed the bidding, and addressed the
dam elevation of 996 feet. The cost of the 996 foot dam was
established at 2. 8 million in October 1989. The basic cost
of this dam should be 2 . 34 million, plus twenty-five
percent. Total City cost for the project was discussed,
stating the City got a better deal in Phase II. In Phase
III , the government estimate was 2. 867 million, and the bids
came in at 3 . 785 million.
Options were presented by Colonel Smith. The bids were
extended for 30 days. They can award Phase III , or let the
bids expire. The issue remains open. He mentioned funding
for McGrath and Plum Creek projects for a combined total of
10 million. He was unsure of what might happen if the local
cooperative agreement were terminated on Holliday Creek. He
noted that federal monies are hard to come by. The bid
document says that the City has to pay 3 . 8 million on the
dam. The City will pay the 993 foot cost, plus twenty-five
percent of the difference. The difference is $600 ,000
today. If the three feet can be cost shared by the Corps on
the Freeboard issue, the 996 cost could be reduced from 3 . 8
million to 3 . 2 million to the City.
Mayor Lam stated we want to keep the project, and we
are not wanting to terminate this agreement. When the first
bid came in they were working with the same embankment
costs. After it was re-bid, the low bid came in at 3 . 8
million for the embankment costs. The City wanted to
cooperate on this estimate from $2 ,340 , 000 base, and add
$500,000. We are trying to get there. The Council feels
they have made some improvement. Phase II is completed, and
they want to move into Phase III . He asked Colonel Smith
what the figures would be if the Corps participates in the
996 foot elevation. Colonel Smith stated that he expects
the answer this week. It was noted that we established in
Phase II how we were going to distribute costs. We used
bids for Phase II. They were prepared to continue to do
that in Phase III .
Colonel Smith explained that as a contracting or
procuring officer it is required that he make a
determination whether a bid is materially imbalanced. If it
is imbalanced, he rejects the bid, and the Council would
want him to do that. Sometimes it might be materially
imbalanced, but not to their disadvantage, and the bids
would not be rejected.
Mr. Bonnett noted that he does not disagree with
Colonel Smith' s presentation a great deal. He reviewed the
process of how we got here in revising the City' s
distribution. Phase II was not an imbalanced bid. It was a
blown bid, and the contractor has eaten one million on it.
He feels it is not appropriate to come back and redistribute
the costs. This bid is probably the best bid that we will
receive, and believes it is fertile ground for making a
compromise. He is afraid the contractors may have heard
something that was not said.
i
569
Colonel Smith stated there was no one in the Corps that
influenced any bidder, and if he finds anyone in his
authority he will run them off. The contractor came to the
conclusion that was what it would cost. His dilemma is now
twofold. He has an agreement with the City that they will
not award a bid for more than $2,340,000. If something is
not done the bids will expire. He hopes the bids can be
reduced to the $600,000 figure. He needs the City' s
commitment to go with the bid, plus $600 ,000 of a 48 million
project.
Colonel Smith noted that they blew the government
estimate on the bridge. Today it would be 1. 5 million. Our
agreement is a two-party agreement, and an award of Phase
III does not terminate that agreement. To back down to a
993 elevation would be a lengthy process, and a very low
probability. It would be $800,000 more if they do not cost
share the Freeboard. The Corps will pay $600,000 ; the City
$200,000. Mr. Berzina requested that consideration be given
to applying the additional costs of securing the land for
the 996 elevation. The Corps will make an examination of
the ability to cost share the Freeboard. They bring
$600,000 to the table if it is possible.
Councilor Thompson noted that the Council is made up of
reasonable men, who have a spirit of cooperation. Colonel
Smith noted that Dr. Steinberg is working on this, and he
also has a spirit of generosity.
Mr. Berzina asked about other alternatives being looked
at by the Corps which may have a different solution than
what has been discussed today. Colonel Smith stated there
are no other options being considered. He also noted that
he is of the opinion that the person who signs his name gets
the final say. He would hate to see the City of Wichita
Falls get caught up in whether it is a technical or policy
decision. He further stated that his objective is not, and
cannot be, to go seek out a methodology on the City' s cost
being reduced. He has to seek out a methodology on being
fair. They have been unsuccessful in the past three weeks
to come up with a methodology on what has been discussed
today. The rationale has to be defendable.
Bids have been delayed for thirty days from today,
October 29, 1990. Colonel Smith noted that they have 130
million in other jobs to be bid out. He hopes to have the
answer to the cost sharing by the end of this week.
Mayor Lam expressed appreciation for their attendance
and presentation.
The City Council reconvened at 10: 25 a.m. , and
adjourned at 10: 27 a.m.
PASSED AND APPROVED this Zl&day of
1990.
Michael Lam, or
ATTEST:
r
Wilma J. Thomas, CMC/AAE
City Clerk