Res 034-2002 4/2/2002RESOLUTION NO. - O L
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF WICHITA
FALLS, TEXAS, TO ACCEPT THE BRIDWELL STREET
RECONSTRUCTION PROJECT (CDBG) AND AUTHORIZE FINAL
PAYMENT TO FREEMAN CONSTRUCTION CO.; FINDING AND
DETERMINING THAT THE MEETING AT WHICH THIS RESOLUTION
WAS PASSED WAS OPEN TO THE PUBLIC AS REQUIRED BY LAW.
WHEREAS, the City of Wichita Falls entered a unit price contract with Freeman
Construction Co. with the estimated total cost of $34,755.00; and
WHEREAS, the actual work was completed at a total cost of $38,180.77, of
which $37,417.15 has been previously paid to the contractor, leaving an amount due of
$763.62; and
WHEREAS, the City staff has inspected the work and found it to be acceptable.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
SECTION 1. The Bridwell Street Reconstruction Project (CDBG) is hereby
accepted, and the City Manager is authorized to make final payment to the contractor.
SECTION 2. It is hereby officially found and determined that the meeting at
which this resolution was passed was open to the public as required by law.
PASSED AND APPROVED this the 2nd day of April, 2002.
MAYOR
ATTEST: