Res 057-2002 5/21/2002RESOLUTION NO. �59-0-60a
RESOLUTION TO ACCEPT THE TAYLOR STREET
RECONSTRUCTION (CDBG) PROJECT AND AUTHORIZE FINAL
PAYMENT TO DUKE CONSTRUCTION; FINDING AND DETERMINING
THAT THE MEETING AT WHICH THIS RESOLUTION WAS PASSED
WAS OPEN TO THE PUBLIC AS REQUIRED BY LAW.
WHEREAS, the City of Wichita Falls entered a unit price contract with Duke
Construction with the estimated total cost of $239,805.45; and
WHEREAS, the actual work was completed at a total cost of $257,915.53 of
which $252,757.22 has been previously paid to the contractor, leaving an amount due
of $5,158.31; and
WHEREAS, the City staff has inspected the work and found it to be acceptable..
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
SECTION 1. The Taylor Street Reconstruction (CDBG) Project is hereby
accepted, and the City Manager is authorized to make final payment to the contractor.
SECTION 2. It is hereby officially found and determined that the meeting at
which this resolution was passed was open to the public as required by law.
PASSED AND APPROVED this the 21st day of May, 2002.