Res 092-2002 9/3/2002RESOLUTION NO. Oka -aWD
RESOLUTION TO ACCEPT THE FM 367 WATER MAIN EXTENSION
PROJECT AND AUTHORIZE FINAL PAYMENT TO GARCIA
CONSTRUCTION CO.; FINDING AND DETERMINING THAT THE
MEETING AT WHICH THIS RESOLUTION WAS PASSED WAS OPEN
TO THE PUBLIC AS REQUIRED BY LAW.
WHEREAS, the City of Wichita Falls entered a unit price contract with Garcia
Construction Co. with the estimated total cost of $209,927.64; and
WHEREAS, the actual work was completed at a total cost of $213,753.18 of
which $192,314.75 has been previously paid to the contractor, leaving an amount due
of $21,438.43; and
WHEREAS, the City staff has inspected the work and found it to be acceptable.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
SECTION 1. The FM 367 Water Main Extension Project is hereby accepted, and
the City Manager is authorized to make final payment to the contractor.
SECTION 2. It is hereby officially found and determined that the meeting at
which this resolution was passed was open to the public as required by law.
PASSED AND APPROVED this the 3rd day of September, 2002.
ATTEST: