Res 066-2015 7/7/2015
Resolution No. 66-2015
Resolution approving Change Order #4 for the Terminal Area Project
at Wichita Falls Regional Airport to Trinity-Hughes/Sundt in an
amount of $485,704
WHEREAS, the City of Wichita Falls entered into a contract with Trinity-
Hughes/Sundt with an estimated total cost of $28,137,103; and,
WHEREAS, the City of Wichita Falls entered into three previous change order
agreements with Trinity-Hughes/Sundt in the amount of $862,210 for various additional
scope of work changes to the Terminal Area Project; and,
WHEREAS, Change Order #4 will add $485,704 to the contract for a revised
cost of $29,485,017; and,
WHEREAS, City staff has reviewed all aspects of this change order and believes
that it is in the City’s best interest to appro ve.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
Change Order #4 for the Terminal Area Project at Wichita Falls Regional Airport
is hereby approved, and the City Manager is authorized to make ame ndments to this
contract with Trinity-Hughes/Sundt, with changes thereto in a form approved by the City
Attorney, in an estimated amount of $485,704.
PASSED AND APPROVED this the 7th day of July, 2015.
______________________________
M A Y O R
ATTEST:
____________________
City Clerk
CITY OF WICHITA FALLS, TEXAS CHANGE ORDER NO.:4
CONTRACT CHANGE ORDER FORM 7/7/2015
$485,704.00
PROJECT/CONTRACT:
TO:_Trinity-Hughes/Sundt_, this Change Order, after approval by the Owner, will be your
(Contractor)
authority to make the following changes in the work under your contract:
Decrease Increase Total Change
in Contract in Contract in Contract
238,169.00$ 238,169.00$
-$ 24,276.00$ 24,276.00$
-$ 599,765.00$ 599,765.00$
-$ 485,704.00$ 485,704.00$
-$ -$ -$
-$ -$ -$
-$ 1,347,914.00$ 1,347,914.00$
$28,137,103.00
485,704.00$
862,210.00$
$29,485,017.00
The completion time under your contract will be extended by 30 days because of this change
order making the revised completion date 90 Calendar Days
Approved By Owner:Accepted By Contractor:Recommended By Arch/Eng:
(if applicable)
By:______________________By:______________________By:_____________________
Title:_____________________Title:_____________________Title:____________________
Date:_____________________Date:_____________________Date:____________________
CONTRACT AMOUNT TO DATE:
6.
TOTAL
AMOUNT OF ORIGINAL CONTRACT:
TOTAL AMOUNT OF THIS CHANGE ORDER:
TOTAL AMOUNT OF PREVIOUS CHANGE ORDERS:
4. Parking gate installation and Resturant Construction
5.
parking meter installation; entry road lettering upgrades on wall
3. See attached documentation to complete terminal area project.
rental car parking lot by an additional 50 apaces
2. Meditation room upgrades; carpeting replacement; restroom
improvements; VIP furniture; advertising monitors; smoker stations;
DATE:
1. Additional site development, concrete paving and drainage
improvements to relocate Rental Car Service Facility; Expand current
Description of Changes
Wichita Falls Regional Airport Terminal Area Project
AMOUNT OF CHANGE: