Res 052-2015 5/5/2015Resolution No. _52-2015_
Resolution awarding bid and contract for the 2015 Transfer Station
Parking Lot Rehabilitation Project to McGrath Concrete Construction
in the amount of $57,920.00
WHEREAS, the City of Wichita Falls has advertised for bids for the 2015
Transfer Station Parking Lot Rehabilitation Project; and,
WHEREAS, it is found that the lowest responsible bidder is Jennifer McGrath,
DBA McGrath Concrete Construction, who made a unit price bid with an estimated total
of $57,920.00.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
The unit price bid for the 2015 Transfer Station Parking Lot Rehabilitation
Project is awarded to Jennifer McGrath, DBA McGrath Concrete Construction, in an
estimated total amount of $57,920.00, and the City Manager is authorized to execute a
contract for the City with said Contractor for the construction of such project.
PASSED AND APPROVED this the 5th day of May, 2015.
______________________________
M A Y O R
ATTEST:
____________________
City Clerk