Res 1378 2/6/1973RESOLUTION NO. /1J 7f
RESOLUTION ALLOWING GILVIN-TERRILL, INC.
EXTENSION OF TIME FOR COMPLETION OF CON-
TRACT FOR RELOCATION OF FORT WORTH AND
DENVER RAILROAD.
WHEREAS, heretofore the City of Wichita Falls and Gilvin-
Terrill, Inc. entered into a contract dated September 15, 1971,
whereby the contractor was to relocate certain Fort Worth and
Denver railroad facilities in connection with the Kell Freeway
construction, which contract required the contractor to substan-
ially complete the work within 225 working days; and,
WHEREAS, Section 4.02 of the general conditions of such
contract provided that, should the contractor be delayed in the
completion of the work by unavoidable causes beyond the contract-
or' s control, an extension of time shall be allowed for complet-
ing the work, sufficient to compensate for the delay, the amount
of the extension to be determined by the engineer, Forrest and
Cotton, Inc. ; and,
WHEREAS, the contractor has requested a contract time exten-
sion of 100 working days, because of delays beyond its control
during the progress of construction, and Forrest and Cotton, Inc.
has recommended that such request be granted.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF
THE CITY OF WICHITA FALLS, TEXAS, THAT:
The request of Gilvin-Terrill, Inc. for a contract time ex-
tension of 100 working days under such contract of September 15,
1971 is hereby allowed and granted.
PASSED AND APPROVED THIS THE 6TH DAY OF FEBRUARY, 1973.