Res 1364 11/7/1972RESOLUTION NO. /?0 7
WHEREAS, the City of Wichita Falls and Costello Construction
Company entered into a contract dated August 15, 1972, wherein said
contractor agreed to construct certain Sanitary Sewer Extensions,
Project 89-168-05; and,
WHEREAS, said improvements have been completed in accordance
with plans and specifications; and,
WHEREAS, a change order and a final estimate have been submitted
on this project, which final estimate shows a total amount of work
done as $4,477. 15, none of which has previously been paid to the
Contractor, leaving a balance of $4,477.15;
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE
CITY OF WICHITA FALLS, TEXAS, THAT:
The construction of such sanitary sewer extensions is accepted
by the City of Wichita Falls, the change order and final estimate is
approved, and the City Manager is directed to pay the said Contractor
the amount due as shown on such estimate.
PASSED AND APPROVED THIS the 7th day of November, 1972.
Of (i
MAYOR
Attest:
City Clerk
DEPARTMENT OF PUBLIC UTILITIES
Project Sanitary Sewer Improvement - Mimosa Heights
Contractor Costello Construction Company
Monthly Estimate No. Final Project No. 89-168-05
Contract Amount $4,399.50 Contract Working Days Working Days Used
Per Cent of Work Completed 100 Per Cent of Time Used Date 11-2-72
cm, Unit Of Project Total Work Done Contract
i Item
Measure I Estimate Quantities On Contract Pnce Amount
GPI
1 16" VCT 4'-6' Depth j L.F. 1 430 430 ) 2. 75 1,182.50
1
2 16" VCT 6'-8' Depth ' L.F. 470 402 I 3.00 ! 1,206.00
I I
2A '6" VCT 8'-10' Depth L.F. 0-100 I 3. 75 375.00
3 'Basic M.H. 0-4' De.th Ea . 2 190.00 I 380.00
3A ICleanout Ea . 0- 1 50.00 50.00
3B ;Si.hon Ea . 0- 1 1 100.00 I 100.00
4 Extra De.th Manholes L.F. 7 3 22.00 j 66.00
5 16" X 4" W e Connections
I
Ea . i 9 9 12.00 ( 108.00
1 i
6 Asphalt Pavement Replacement i S.Y. 300. 310.66 3.25 1,009.65
f I
I I
i I I I
I 1
1
i I I
1 I
i I 1
i I I i
Total Amount of Work Done 4 477. 15
repared By Less Retainage 0-
Difference 4,477. 15
Submitted By Less Special Deductions 0-
Less Liquidated Damage
A .ovcd By: Joe C. Smith Less Previous Payments 0-
rector of Public Utilities
Amount tue This Estimate 4,477.15
CHANGE ORDER
Tabulated below is a final change order brought about by
various field changes:
A. Added Quantities
Item Description Total Work Unit Total
Done Price
2A 6" VCT-Depth 8'-10' 100 Ft. 3. 75 375.00
3A Cleanout 1 Ea. 50.00 50.00
3B Siphon 1 Ea.100.00 100.00
6 Asphalt Repairs 10.66 S.Y. 3.25 34.65
Total 559.65
B. Deleted Quantities
Item Description Total Work Unit Total
i Done Price
2 6" VCT-Depth 6'-8' 68 L.F. 3.00 204.00
3 Basic Manhole 1 Ea.190.00 190.00
4 Extra Depth Manhole 4 L.F.22.00 88.00
Total 482.00
DIFFERENCE:
Added 559.65
Deleted $ 482.00
Diff. 77.65
7 ' ,/Approved By: >/ ` ( ( . C ,. 47(
Joe C. Smith
Director of Public Utilities
G44!4 E COSTELLO
L.vHTH STREET
F,HONF.. 322.8448
COSTELLO CONSTRUCTION COMPANY
RSe et and ripe c.itae a,osilt,ialjrl a Specialty"
POST OFFICE BOX 888 PHONE 322-8449
WICHITA FALLS, TEXAS 76301
Oct. 30, 1972.
Gerald Fox
City Manager,
City of Wichita Fa 1.ls , Tex s.
Sanitary Sewer Improvements.,for Mimosa Htts. Additton-City of
Wichita Falls, Texas.
i-- 430 feet 6" V. C. Sewer- Depth 4'to 6' $2.75@ 1,182.50
2- 470' " I' Dppth 6' to 8' 3.00@ 1,410.00
3- - Basic Manholes 0-4' depth 190.00 380.00
4- 3 L.F. extra Depth T .H. 422.00 66.00
5- 9- 6x4 Wyes 12.00 - 108.00
6- 300 S. Y. Asphalt Repairs 3.25 975.00
Extras-32 extra feet 6" 6' to v' 3.00 96.00
100 feet extra depth 8' to 9'' 75 75.00
1 Clean out 50.00
1- Siphon 100.00
32 Extra. feet AsOlialt 10 2-3 S. Y. 3.25@
X4,377655
This letter is to certify that se'-'ers were installed according to City' s
lines and grades , and under City' s specifications and Inspector. That
all labor, equipment and materials have been paid.
Cos/'teilp Construction Company
By 7 L 4 r r
1 f1
APPROVED BY:
I"
Joe C. Smith
Director of Public Utilities