Res 1619 2/4/1975RESOLUTION NO. //;/9
RESOLUTION APPROVING CHANGE ORDER AND ACCEPTING
SANITARY SEWER FACILITIES AT TEXAS STATE HOSPITAL AREA
WHEREAS, the City of Wichita Falls and Opex, Inc. , entered
a contract dated May 21, 1974, wherein said contractor agreed to construct
Sanitary Sewer Facilities in Texas State Hospital Area; and,
WHEREAS, said facilities have been completed in accordance
with plans and specifications; and
WHEREAS, final change order and final estimate have been
submitted on this project, which final estimate shows a total amount
of work done as $57,228,50, of which $50,179. 72 has been paid to the
contractor, leaving a balance of $7,048. 78;
NOW THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE
CITY OF WICHITA FALLS THAT:
The construction of such sanitary sewer facilities is
accepted by the City of Wichita Falls, the change order and the
final estimate are approved, and the City Manager is directed to pay
the said contractor the amount due as shown on such estimate.
PASSED AND APPROVED THIS THE 4TH DAY OF FEBRUARY, 1975.
de
M "=Y4 R d7- 711
ATTEST:
e.z
City Clerk
DEPARTMENT OF PUBLIC UTILITIES
Project Texas State Hospital Area Sewer Facilities
Contractor 0pex, Inc.
Monthly . Estimate No. 6 & Final Project No.
Contract Amount $52,745. 75 Contract Working Days 120 Working Days Used 179
Per. Cent of Work Completed 108 Per Cent of Time Used 136 Date 1-28-75
m I Unit Of Project Total Work Dona Contract
L—
INa.
Item
Measure Estimate Contract Pnco AmountMeasureEstimateQuantities
1 ; 4" VC Pipe (0-6') LF I 613 ( 710 I 2. 75 ! 1,952.50
2 i 6" VC Pipe (0-6')I LF I 1913 1,718 3.00 I 5,154.00
3 ' 6" VC Pipe (6'-8') LF 1263 • 1 1,363 5.00 I 6,815.00
4 t 6" VC Pipe (8'-10') I LF 481 I .5.5U 7.00 I 3,850.00
5 ' 6" VC Pipe (10'-12') l LF I 897 ; 916 11.00 j 10,076.00
6 I 6" VC Pipe (12'-14') LF 641 568 14.00 j 7,952.00
7 ; 6 X 4 VC Wyes EA • 59 63 1 10.00 ( 630.00
8 ' Standard Manholes . EA 18 17 325.00 5,525.00
9 ; _xtra De.th. Manholes I LF 47.5 I 42.3 I 40.00 ; 1,692.00
101 4" Stubs Out of Manhole EA 9 ( 3 20.00 60.00
11: Cleanout Complete EA 10 10 I 70.00 I 700.00
12; 6" CI Pipe' LF 110 110 ( 35.00 I 3,850.00
131 Pavement Cutting & Replacement LF 128 I 125 ; 16.00 I 2,000.00
14! Concrete Furnished In Place I CY I 15. I 18.75 ( 40.00 I 750.00
15' Crushed Stone Furnished in Place CY 120 I 158 I 9.00 I 1,422.00
Sub-Total I 52,428.50
i I
I I
Rock Excavation I C.Y. 1100 600 I 8.00 I 4,800.00
I I I
I i
I I
1 11 I I
I i
I I j I
1 j I j j
i I
I I I
I i I i I
I I I
i I I
1 I I I
I I I I I
I I I
Total Amount of Work Done 57,228.5C
pared By Less Retainage O-
Difference 0-
Submitted By Less Special Deductions 0-
A Less Liquidated Damage 0-
proved By: Joe C. Smith Less Previous Payments 50,179.72
irector of Public Utilities
Amount Tate This B:.tjmate „ wow $
7,048.78
Final Change Order
Sewer Facilities
Texas State Hospital Area
Item Unit Estimated Work Plus Minus
No. Price Quantity Done Cost Cost
1. 2. 75 613 710 266.75
2. 3.00 1913 1718 585.00
3. 5.00 1263 1363 500.00
4. 7.00 481 550 483.00
5. 11.00 897 916 209.00
6. 14.00 641 568 1,022.00
7. 10.00 59 63 40.00
8. 325.00 18 17 325.00
9. 40.00 47.5 42.3 208.00
10. 20.00 9 3 120.00
11. 70.00 10 10
12. 35.00 110 110
13. 16.00 128 125 48.00
14. 40.00 15 18.75 150.00
15. 9.00 120 158 342.00
1,990.75 2,308.00
Adjustment:
Deductions $ 2,308.00
Additions 1,990. 75
317.25
Rock Excavation:
600 C.Y. @ $8.00 = $4,800.00
Total Difference = $4,800.00
317.25
4,482.75
Contract Price = $52,745.75
Plus 4,482.75
Total Contract = $57,228.50
1 , , C
e C. Smith, P.E.
Director of Public Utilities
2, i, ,,di•, 7..,-145) y NAV;Jo TA FALLS, iE t.":C
75SC'i
t ' `
J ., ,
M.. ,.- . is
r
engineers surveyors planners
i
January 15, 1975
ESTIMATE NO. 6 (FINAL)
SEWER FACILITIES
TEXAS STATE HOSPITAL AREA SEWER FACILITIES
WICHITA FALLS, TEXAS
OWNER: City of Wichita Falls CONTRACT TIME: 120 days
CONTRACTOR: Opex, Inc. TIME USED TO DATE: 179 days
CONTRACT AMOUNT: $ 52, 745. 75
UNIT
ITEM NO. QUANTITY DESCRIPTION PRICE AMOUNT
1 710 LF 4" VC Pipe (0-6 ' ) 2.75 1, 952.50
2 1718 LF 6" VC Pipe (0-6 ' ) 3.00 5, 154.00
3 1363 LF 6" VC Pipe (6 ' -8 ' ) 5.00 6,815.00
4" 550 LF 6" VC Pipe (8 ' -10 ' ) 7.00 3,850.00
5 916 LF V Pipe (10 ' -12 ' ) 11.00 10,076.00
6 568 LF 6" VC Pipe ( 12 ' -14' ) 14.00 7, 952.00
7 63 EA 6" x 4" Wyes 10.00 630.00
8 17 EA Standard Manholes 325.00 5, 525.00
9 42. 3 LF Extra Depth Manholes 40.00 1, 692.00
10 3 EA 4" Manhole Stubs 20.00 60.00
11 10 EA Cleanouts 70.00 700.00
12 110 LF 6" Cast Iron Pipe 35.00 3, 850.00
13 125 LF Pavement Cutting and Replacement 16.00 2,000.00
14 18. 75 CY Concrete 40.00 750.00
15 158 CY Crushed Stone 9.00 1,422.00
600 CY Rock Excavation 8.00 4,800.00
TOTAL 57, 228. 50
Less Previous Payments 50, 179.72
AMOUNT THIS ESTIMATE 7,048.78
1It6. 1, / -
YttC LA
A. E. Probst, Jr, P. .
AEP/aa
cc : Opex, Inc.
ROSS H. CORLETT, JR
HARRY L GRAY
A. E. PROBST, JR