Res 1619 2/4/1975RESOLUTION NO. //;/9 RESOLUTION APPROVING CHANGE ORDER AND ACCEPTING SANITARY SEWER FACILITIES AT TEXAS STATE HOSPITAL AREA WHEREAS, the City of Wichita Falls and Opex, Inc. , entered a contract dated May 21, 1974, wherein said contractor agreed to construct Sanitary Sewer Facilities in Texas State Hospital Area; and, WHEREAS, said facilities have been completed in accordance with plans and specifications; and WHEREAS, final change order and final estimate have been submitted on this project, which final estimate shows a total amount of work done as $57,228,50, of which $50,179. 72 has been paid to the contractor, leaving a balance of $7,048. 78; NOW THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE CITY OF WICHITA FALLS THAT: The construction of such sanitary sewer facilities is accepted by the City of Wichita Falls, the change order and the final estimate are approved, and the City Manager is directed to pay the said contractor the amount due as shown on such estimate. PASSED AND APPROVED THIS THE 4TH DAY OF FEBRUARY, 1975. de M "=Y4 R d7- 711 ATTEST: e.z City Clerk DEPARTMENT OF PUBLIC UTILITIES Project Texas State Hospital Area Sewer Facilities Contractor 0pex, Inc. Monthly . Estimate No. 6 & Final Project No. Contract Amount $52,745. 75 Contract Working Days 120 Working Days Used 179 Per. Cent of Work Completed 108 Per Cent of Time Used 136 Date 1-28-75 m I Unit Of Project Total Work Dona Contract L— INa. Item Measure Estimate Contract Pnco AmountMeasureEstimateQuantities 1 ; 4" VC Pipe (0-6') LF I 613 ( 710 I 2. 75 ! 1,952.50 2 i 6" VC Pipe (0-6')I LF I 1913 1,718 3.00 I 5,154.00 3 ' 6" VC Pipe (6'-8') LF 1263 • 1 1,363 5.00 I 6,815.00 4 t 6" VC Pipe (8'-10') I LF 481 I .5.5U 7.00 I 3,850.00 5 ' 6" VC Pipe (10'-12') l LF I 897 ; 916 11.00 j 10,076.00 6 I 6" VC Pipe (12'-14') LF 641 568 14.00 j 7,952.00 7 ; 6 X 4 VC Wyes EA • 59 63 1 10.00 ( 630.00 8 ' Standard Manholes . EA 18 17 325.00 5,525.00 9 ; _xtra De.th. Manholes I LF 47.5 I 42.3 I 40.00 ; 1,692.00 101 4" Stubs Out of Manhole EA 9 ( 3 20.00 60.00 11: Cleanout Complete EA 10 10 I 70.00 I 700.00 12; 6" CI Pipe' LF 110 110 ( 35.00 I 3,850.00 131 Pavement Cutting & Replacement LF 128 I 125 ; 16.00 I 2,000.00 14! Concrete Furnished In Place I CY I 15. I 18.75 ( 40.00 I 750.00 15' Crushed Stone Furnished in Place CY 120 I 158 I 9.00 I 1,422.00 Sub-Total I 52,428.50 i I I I Rock Excavation I C.Y. 1100 600 I 8.00 I 4,800.00 I I I I i I I 1 11 I I I i I I j I 1 j I j j i I I I I I i I i I I I I i I I 1 I I I I I I I I I I I Total Amount of Work Done 57,228.5C pared By Less Retainage O- Difference 0- Submitted By Less Special Deductions 0- A Less Liquidated Damage 0- proved By: Joe C. Smith Less Previous Payments 50,179.72 irector of Public Utilities Amount Tate This B:.tjmate „ wow $ 7,048.78 Final Change Order Sewer Facilities Texas State Hospital Area Item Unit Estimated Work Plus Minus No. Price Quantity Done Cost Cost 1. 2. 75 613 710 266.75 2. 3.00 1913 1718 585.00 3. 5.00 1263 1363 500.00 4. 7.00 481 550 483.00 5. 11.00 897 916 209.00 6. 14.00 641 568 1,022.00 7. 10.00 59 63 40.00 8. 325.00 18 17 325.00 9. 40.00 47.5 42.3 208.00 10. 20.00 9 3 120.00 11. 70.00 10 10 12. 35.00 110 110 13. 16.00 128 125 48.00 14. 40.00 15 18.75 150.00 15. 9.00 120 158 342.00 1,990.75 2,308.00 Adjustment: Deductions $ 2,308.00 Additions 1,990. 75 317.25 Rock Excavation: 600 C.Y. @ $8.00 = $4,800.00 Total Difference = $4,800.00 317.25 4,482.75 Contract Price = $52,745.75 Plus 4,482.75 Total Contract = $57,228.50 1 , , C e C. Smith, P.E. Director of Public Utilities 2, i, ,,di•, 7..,-145) y NAV;Jo TA FALLS, iE t.":C 75SC'i t ' ` J ., , M.. ,.- . is r engineers surveyors planners i January 15, 1975 ESTIMATE NO. 6 (FINAL) SEWER FACILITIES TEXAS STATE HOSPITAL AREA SEWER FACILITIES WICHITA FALLS, TEXAS OWNER: City of Wichita Falls CONTRACT TIME: 120 days CONTRACTOR: Opex, Inc. TIME USED TO DATE: 179 days CONTRACT AMOUNT: $ 52, 745. 75 UNIT ITEM NO. QUANTITY DESCRIPTION PRICE AMOUNT 1 710 LF 4" VC Pipe (0-6 ' ) 2.75 1, 952.50 2 1718 LF 6" VC Pipe (0-6 ' ) 3.00 5, 154.00 3 1363 LF 6" VC Pipe (6 ' -8 ' ) 5.00 6,815.00 4" 550 LF 6" VC Pipe (8 ' -10 ' ) 7.00 3,850.00 5 916 LF V Pipe (10 ' -12 ' ) 11.00 10,076.00 6 568 LF 6" VC Pipe ( 12 ' -14' ) 14.00 7, 952.00 7 63 EA 6" x 4" Wyes 10.00 630.00 8 17 EA Standard Manholes 325.00 5, 525.00 9 42. 3 LF Extra Depth Manholes 40.00 1, 692.00 10 3 EA 4" Manhole Stubs 20.00 60.00 11 10 EA Cleanouts 70.00 700.00 12 110 LF 6" Cast Iron Pipe 35.00 3, 850.00 13 125 LF Pavement Cutting and Replacement 16.00 2,000.00 14 18. 75 CY Concrete 40.00 750.00 15 158 CY Crushed Stone 9.00 1,422.00 600 CY Rock Excavation 8.00 4,800.00 TOTAL 57, 228. 50 Less Previous Payments 50, 179.72 AMOUNT THIS ESTIMATE 7,048.78 1It6. 1, / - YttC LA A. E. Probst, Jr, P. . AEP/aa cc : Opex, Inc. ROSS H. CORLETT, JR HARRY L GRAY A. E. PROBST, JR