Res 1734 10/21/1975RESOLUTION NO. /%5V-
RESOLUTION APPROVING CHANGE ORDERS AND
FINAL ESTIMATE AND ACCEPTING CONSTRUC-
TION OF REPAIRS TO THE LAKE DIVERSION
SPILLWAY STRUCTURES.
WHEREAS , the City of Wichita Falls and the Wichita
County Water Improvement District No. 2, as owners, and
Navarro Contracting Co. , as contractor, entered into a
contract dated September 19, 1973 , wherein said contractor
agreed to construct certain repairs to the Lake Diversion
spillway structures; and,
WHEREAS , said construction has been completed in
accordance with the plans and specifications; and,
WHEREAS , Change Order No. 1 has heretofore been approved
by the Board of Aldermen; and,
WHEREAS , Change Orders No. 2, No. 3 and No. 4 and the
final estimate have been submitted on this project, which
final estimate shows a total amount of work done as $706, 092. 00 ,
of which $679 , 712 . 00 has been paid to the contractor, leaving
a balance of $26 , 380. 00; and,
WHEREAS , the City owes 66. 11% of the balance due, or
17 , 439 . 82, and the Water District owes 33. 89% , or $8 ,940 . 18 ;
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN
OF THE CITY OF WICHITA FALLS , TEXAS , THAT:
The construction of repairs to the Lake Diversion spill-
way structures is accepted by the City of Wichita Falls, Change
Orders No. 2, No. 3 and No. 4 and the final estimate are ap-
proved, and the City Manager is directed to pay to the said
contractor the City' s share of the amount due as shown on such
estimate.
PASSED AND APPROVED this the 21st day of October, 1975.