Res 1814 5/18/1976RESOLUTION NO. ///i
RESOLUTION APPROVING FINAL ESTIMATE AND
ACCEPTING CONSTRUCTION OF EMERGENCY ROADS
AT LAKE KEMP.
WHEREAS, the City of Wichita Falls and Zack Burkett
Company entered into a contract dated December 2, 1975,
wherein the contractor, Zack Burkett Company, agreed to
construct certain emergency roads at Lake Kemp; and,
WHEREAS, said construction has been completed in
accordance with the plans and specifications; and,
WHEREAS, the contractor has submitted the final
estimate on this project, which final estimate shows a
total amount of work done as $18, 560. 00, of which $4, 640. 00
has been paid by the City to the contractor, leaving a
balance due of $13, 920. 00; and,
WHEREAS, the City is responsible for payment of
66. 11% of the cost of these improvements (being $12,270. 00) ,
and Wichita County Water Improvement District No. 2 is
responsible for payment of 33. 89% of such cost (being
6, 290. 00) .
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF
ALDERMEN OF THE CITY OF WICHITA FALLS, TEXAS, THAT:
The construction of the emergency roads at Lake Kemp
is accepted by the City of Wichita Falls, the final estimate
is approved, and the City Manager is directed to pay to
Zack Burkett Company the balance due as shown on such
final estimate and to charge Wichita County Water
Improvement District No. 2 the sum of $6, 290. 00.
PASSED AND APPROVED this the //1+-/day of At
1976.
f
dy1(
0 R 117;"/Y-7'
ATTEST:
City Clerk