Res 1769 2/3/1976RESOLUTION NO. /76r
RESOLUTION APPROVING CHANGE ORDER NO. 1 WITH STUCKEY
CONSTRUCTION COMPANY, INC. , CONCERNING THE 1975 COM-
MUNITY DEVELOPMENT ASSESSMENT PAVING PROGRAM
BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE CITY OF
WICHITA FALLS, TEXAS, THAT:
Change Order No. 1 , a copy of which is attached hereto,
between the City of Wichita Falls and Stuckey Construction Company, Inc. ,
amending the contract for construction of the 1975 Community Development
Assessment Paving Program to provide for construction of streets and
parking lots in Scotland and Tesco parks, is hereby approved, and the
City Manager is authorized to execute the same for the City of Wichita
Falls.
PASSED AND APPROVED this the 3rd day of 'February, 1976.
A 7MAYOR "r
Attest:
y iT'C
1 City Clerk
CHANGE ORDER NO. 1
January 28, 1976
1975 COMMUNITY DEVELOPMENT ASSESSMENT PAVING PROGRAM
WICHITA FALLS, TEXAS
1 . INTENT
It is the intent of this Change Order to amend the contract dated
November 19, 1975 to include the additional quantities and additional
items described as follows :
APPROX.
PAY ADDL. ITEM WITH BID PRICES UNIT AMOUNT
ITEM QUANTITY WRITTEN IN WORDS BID BID
1 5,678 LF Standard Curb and Gutter at
Two Dollars and Forty Cents per
L. F. 2.40 13,627.20
2 571 SF Standard Valley Gutter at One
Dollar and Ten Cents per S. F. $ 1 . 10 628. 10
4 420 SF 4 inch Concrete Sidewalk at No
Dollars and Seventy-five Cents
per S. F. 0. 75 315.00
5 904 SF Standard Concrete Driveway Ap- -
proaches at One Dollar and Ten
Cents per S. F. 1 . 10 994.40
6 44.5 LF 18 inch Reinforced Concrete Pipe
at Nine Dollars and no Cents per ,
L. F. 9.00 400.50
9 5,910 SY Type ' D' H.M.A.C. Surface Course
on 4 inches Asphalt Stabilized
Gravel Base on 4 inches of Sand-
stone foundation course at Five
Dollars and Ninety Cents per
S.Y. 5.90 34,869.00
NEW PAY APPROX. ITEM WITH NEGOTIATED PRICES UNIT
ITEM QUANTITY WRITTEN IN WORDS PRICE AMOUNT
11 3,985 SY 2" Type ' D' H.M.A.C. Surface
Course on 6" of sandstone found-
ation course including excavation
at Three Dollars and Forty Cents
per S.Y. 3.40 13,549.00
NEW PAY APPROX. ITEM WITH NEGOTIATED PRICES UNIT
ITEM QUANTITY WRITTEN IN WORDS PRICE AMOUNT
12 2.6 CY Concrete for headwalls including
reinforcing steel at Three hun-
dred twenty-five Dollars and no
Cents per CY. 325.00 $ 845.00
13 35.7 LF Class A Pipe Bedding at Ten
Dollars and Fifty Cents per L. F. $ 10.50 $ 374.85
14 132 LF 6" Doweled Curb at Two Dollars
and Forty Cents per L. F.2.40 $ 316.80
15 90.6 SY Remove old Concrete Pavement at
One Dollar and Fifty Cents per
S.Y. 1 .50 $ 135.90
TOTAL ADJUSTMENT (CHANGE ORDER NO. 1) 66,055.75
TOTAL BID (ORIGINAL CONTRACT) 293,340.00
CONTRACT AMOUNT (ADJUSTED) 359,395.75
2. AGREEMENT
By the signatures of duly authorized agents, the City of Wichita Falls , Owner,
and Stuckey Construction Company, Inc. , Contractor, do hereby agree and append
this Change Order No. 1 to their contract dated November 19, 1975.
STUCKEY CONSTRUCTION COMPANY, INC. CITY OF WICHITA FALLS, TEXAS
Contractor Owner
BY: L/ t,', '.`'- BY:
Date: / — 4 - ? 6 Date:
Attest:Q,*.- i'0.. , 4':.r,.
4=Attest: