RESOLUTION NO.
RESOLUTION APPROVING CHANGE ORDER NO. 1 AND FINAL
ESTIMATE AND ACCEPTING CONSTRUCTION OF SANITARY
SEWER IMPROVEMENTS TO SERVE LOCKWOOD CORPORATION.
WHEREAS, the City of Wichita Falls and Bowles Construction
Co. entered into a contract dated April 21, 1976 , wherein the
contractor agreed to construct sanitary sewer improvements to
serve Lockwood Corporation; and,
WHEREAS , said construction has been completed in accordance
with the plans and specifications; and,
WHEREAS, the contractor has submitted Change Order No. 1
and the final estimate on this project, which final estimate
shows the total amount of work done as $49, 808. 83 , of which
46, 586. 89 has been paid by the City to the contractor, leav-
ing a balance due of $3 , 221. 94.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN
OF THE CITY OF WICHITA FALLS, TEXAS, THAT:
The construction of sanitary sewer improvements to serve
Lockwood Corporation is accepted by the City of Wichita Falls,
the Change Order No. 1 and the final estimate are approved, and
the City Manager is directed to pay to Bowles Construction Co.
the balance due as shown on such final estimate.
PASSED AND APPROVED this the 16th day of May, 1977.
9/4/ ./d17
A Y O R
ATTEST: