Res 2124 4/3/1978RESOLUTION NO. o//c14
RESOLUTION APPROVING CHANGE ORDER NO. 2 TO ZACK
BURKETT CO. CONTRACT RELATIVE TO PHASE III
MUNICIPAL AIRPORT IMPROVEMENTS.
WHEREAS, heretofore the City of Wichita. Falls and Zack Burkett Co. entered
into a contract dated January 23, 1978 for construction of Phase III Municipal Air-
port Improvements; and,
WHEREAS, it is deemed advisable to modify the original plans for such
improvements to eliminate the utilization of on-site base material and provide for
lime stabilized base material; and,
WHEREAS, this modification will increase the construction fees by $6,952.42.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF
THE CITY OF WICHITA FALLS, TEXAS, THAT:
Change Order No. 2, a copy of which is attached hereto, to such contract with
Zack Burkett Co. , are hereby approved, and the City Manager is authorized to
execute Change Order No. 2 on behalf of the City of Wichita Falls.
PASSED AND APPROVED this the 3rd day of April, 1978.
4 0/LI Cr
A Y O R
ATTEST:
City Clerk
CONTRACT CHANGE ORDER ORDER NO. 2
DATE March 24, 1978
CONTRACT FOR: Phase III Improvements - Wichita Falls
Municipal Airport
OWNER: City of Wichita Falls
TO: Zack Burkett Company
Contractor)
You are hereby requested to comply with the following changes from the contract
plans and specifications:
DESCRIPTION OF CHANGES DECREASE INCREASE
Supplemental Plans & Specifications Attached):in Contract Price: in Contract Price
Add - Lime Stabilized Base
1) 113 Tons of lime @ $54.50/Ton 6,158.50
2) 12510 SY of mixing in base @
0.65/SY 8,131.50
Deduct - $1.88 from unit price of Item 1
1) 2701 CY @ $1.88/CY 5,077.88
2) 1915 CY @ $1.18/CY 2,259.70
TOTALS $ 7,337.58 14,290.00
NET CHANGE IN CONTRACT PRICE $ 6,952.42
JUSTIFICATION: There was not enough on-site base available so lime stabilization
was determined to be the next best cheapest solution.
The amount of the Contract will be ( Increased) by the Sum of: Six Thousand
Nine Hundred Fifty Two and 42/100 Dollar,(.; 6,952.42 )
The Contract Total including this and previous Change Orders will be: One Hundred
Fifty Five Thousand Three Hundred Thirty Three and 54/100 Dollars($ 155,333.54 )
The Contract Period provided for completion will be (›Dii6i>."
Unchanged) Days.
This document will become a supplement to the contract and all provisions will
apply hereto.
Requested:(Owr.?r)
Date)
Recommended:(FNGINEER)
Date)
Accepted:(Coa tractor)
Date)