Res 2012 9/6/1977RESOLUTION NO. j/4
RESOLUTION APPROVING FINAL ESTIMATE AND ACCEPTING
POLICE BUILDING REPAIR AND EXPANSION.
WHEREAS, the City of Wichita Falls and M. A. Vordenbaum
Sons, Inc. , entered into a contract dated January 18 , 1977,
wherein the contractor, M. A. Vordenbaum & Sons, Inc. , agreed
to repair and expand the Wichita Falls police headquarters
building located at 610 Holliday Street in Wichita Falls,
Texas; and,
WHEREAS, said repair and expansion has been completed
in accordance with the plans and specifications as certified
by the City' s architect, Charles Harper Associates; and,
WHEREAS, the contract price for such construction was
129 ,282. 00; two change orders amounting to $2,518 . 73 were
made, making the total amount due on said contract $131,800. 73.
Of this amount, $118 ,620. 66 has been paid, leaving a balance
due the contractor of $13,180. 07.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN
OF THE CITY OF WICHITA FALLS, TEXAS, THAT:
The repair and expansion of the Wichita Falls police
headquarters building is accepted by the City of Wichita Falls,
the two change orders are approved, and the City Manager is
directed to pay to M. A. Vordenbaum & Sons, Inc. the balance
due in the amount of $13,180. 07.
PASSED AND APPROVED this the 6th day of September, 1977.
A Y O R 7:4/1
ATTEST:
City lerk