Loading...
Res 2206 9/5/1978F' RESOLUTION NO. cgm' RESOLUTION APPROVING CHANGE ORDER NUMBER 1 AND AUTHORIZING THE CITY MANAGER TO MAKE FINAL PAYMENT TO C AND R CONSTRUCTION AND MANAGEMENT CO. FOR DEMOLITION AND SITE WORK. WHEREAS, on April 11 , 1978, the City of Wichita Falls entered into a contract with C and R Construction and Management Co. for demolition and site work at 719 Ohio, also known as Phase I, Farmers Market; and, WHEREAS, certain items of salvage value were removed from the building by the former owner; and, WHEREAS, the pilasters are no longer necessary to support the remaining wall; and, WHEREAS, the contractor has agreed to accept these two changes with no C change in the contract amount of $24,000; and, WHEREAS, the contractor has submitted his final work estimate showing the amount of $7,767.60 now due for work performed under the contract. NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The demolition and site work at 719 Ohio is accepted by the City of Wichita Falls, the Change Order Number 1, and Final Estimates are approved, and the City Manager is directed to pay to the contractor the amount shown on the estimate.r PASSED AND APPROVHD THIS THE 5th DAY OF September, 1978. MAYOR ATTEST: CITY CL RK s2o- ay. is