Res 2177 7/11/1978RESOLUTION NO. O /I /
RESOLUTION APPROVING CHANGE ORDER AND FINAL ESTIMATE AND
ACCEPTING CONSTRUCTION OF WATER FACILITIES FOR CITY VIEW
HEIGHTS ADDITION
WHEREAS, the City of Wichita Falls and Bowles Construction Company,
as contractor, entered into a contract dated February 1, 1978, wherein
said contractor agreed to construct water distribution mains in City
View Heights Addition; and,
WHEREAS, said construction has been completed in accordance with
plans and specifications; and,
WHEREAS, a change order and the final estimate have been submitted
on this project, which final estimate shows a total amount of work done
as $139,512.39 of which $132,847.96 has been paid, leaving a balance of
6,664.43 to be paid to the contractor.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE
CITY OF WICHITA FALLS, TEXAS, THAT:
The construction of the water distribution mains in City View
Heights Addition is accepted by the City of Wichita Falls, the change
order and final estimate are approved, and the City Manager is directed
to pay to the contractor the amount shown on such estimate.
PASSED AND APPROVED THIS THE 11th DAY OF JULY, 1978.
MAYOR
ATTEST:
i
CITY CLERK
pa
116.