Loading...
Res 2146 5/16/19781 RESOLUTION NO. af/ca RESOLUTION APPROVING CHANGE ORDER NO, 3 TO ZACK BURKETT CO. CONTRACT RELATIVE TO PHASE III MUNICIPAL AIRPORT IMPROVE- MENTS. WHEREAS, heretofore the City of Wichita Falls and Zack Burkett Co. entered into a contract dated January 23, 1978 for construction of Phase III Mun- icipal Airport Improvements; and, WHEREAS, the paving portion of this contract has been completed and final adjustments for as built quantities have been measured on the site; and, WHEREAS, this measurement indicates that the actual quantities utilized in the project exceed the estimated quantities; and, WHEREAS, the measured quantity of materials used will increase the construction fees by $673.10. NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE CITY OF WICHITA FALLS, TEXAS, THAT: Change Order No. 3, a copy of which is attached hereto, to such contract with Zack Burkett Co. , Is hereby approved, and the City Manager is authorized to execute Change Order No. 3 on behalf of the City of Wichita Falls. PASSED AND APPROVED this the 16th day of May 1978. M A Y O ROR ATTEST: City Clerk CONTRACT CHANGE ORDER Phase III Improvements - ORDER NO. 3 Wichita Falls Municipal Airport DATE May 4, 1978 CONTRACT FOR: Phase III Improvements - Wichita Falls Municipal Airport OWNER: City of Wichita Falls TO: Zack Burkett Company Contractor) You are hereby requested to comply with the following changes from the contract plans and specifications: DESCRIPTION OF CHANGES DECREASE INCREASE Supplemental Plans & Specifications Attached):in Contract Price: in Contract Price ADD Concrete Pavement 26 SY @ 18.73/SY 486.98 Prime Coat 48 Gal @ 0.94/Gal 45.12 Tack Coat 150 C.R1 @ 0.94/Gal 141.00 TOTALS $ 673.10 NET CHANGE IN CONTRACT PRICE $ 673.10 JUSTIFICATION: Adjustments for Final as built quantities as measured on site. The amount of the Contract will be ( )(Increased) by the Sum of: Six Hundred Seventy Three and 10/100 Dollar;( ;, 673.10 The Contract Total including this and previous Change Orders will be: One Hundred Fifty Six Thousand Six and 64/100 Dollars($156,006.64 ) The Contract Period provided for completion will be Unchanged) Days. This document will become a supplement to the contract and all provisions will apply hereto. i CV41Requested:(Owrer) I a/ Date) Recommended:(ENGINEER) 44 , lSi l D to) Accepted:(Co,:tractor)F,/:f Date)