Res 2464 2/19/1980RESOLUTION NO. 41-k
RESOLUTION APPROVING CHANGE ORDER NO. 1 AND
FINAL ESTIMATE AND ACCEPTING CONSTRUCTION OF
FORCE MAIN AND SEWER PUMP STATION ON AIRPORT
ROAD
WHEREAS, the City of Wichita Falls, as owner and Bowles
Construction Company, Inc. , as contractor, entered into a contract
dated April 4, 1979, wherein said contractor agreed to construct a
8" force main and sewer pump station; and,
WHEREAS, said construction has been completed in accordance
with the plans and specifications; and,
WHEREAS, Change Order No. 1 and the final estimate has been
submitted on this project, which final estimate and change order shows
a total amount of work done as $69,296.29, of which $61,466.66 has been
paid to the contractor, leaving a balance of $7,829.63.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE
CITY OF WICHITA FALLS, TEXAS, THAT:
The construction of the force main and sewer pump station on
Airport Road is accepted by the City of Wichita Falls, Change Order #1
and Final Estimate is approved, and the City Manager is directed to pay
to said contractor the amount due as shown on estimate.
PASSED AND APPROVED this 19th day of February, 1980.
MAYOR
ATTEST:
City Clerk