Res 2463 2/19/1980RESOLUTION NO.
RESOLUTION APPROVING FINAL ESTIMATE AND ACCEPTING
CONSTRUCTION OF WATER PUMPING STATION AND FACILITIES
LOCATED IN EXPRESSWAY EAST INDUSTRIAL DISTRICT
WHEREAS, the City of Wichita Falls and Decker Construction
Company, l.nc. , as contractor, entered into a contract dated April 20, 1979,
wherein said contractor agreed to construct water pumping station and facilities
located in Expressway East Industrial District; and,
WHEREAS, said construction has been completed in accordance with
the plans and specifications; and,
WHEREAS, the final estimate has been submitted on this project,
which final estimate shows a total amount of work done as $145,900.00 of
which $126,720.00 has been paid to the contractor, leaving a balance of
19,180.00.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE
CITY OF WICHITA FALLS, TEXAS, THAT:
The construction of pump station and facilities in Expressway
East Industrial District is accepted by the City of Wichita Falls, the
final estimate is approved, and the City Manager is directed to pay to the
said contractor the amount due as shown on such estimate.
PASSED AND APPROVED this the 19th day of February, 1980.
MAYOR
ATTEST:
City Clerk
7 aJ