RESOLUTION APPROVING FINAL ESTIMATE AND
ACCEPTING REPAIRS AND PAINTING OF ELEVATED
WATER TANK AT BEVERLY AND SEYMOUR HIGHWAY
WHEREAS, the City of Wichita Falls and Water Tank
Service Company, Inc. , as contractor, entered into a
contract dated February 8, 1979, wherein said contractor
agreed to repair and paint said water tank; and,
WHEREAS, said repairs and painting has been completed
in accordance with specifications; and,
WHEREAS, the final estimate has been submitted on this
project, which final estimate shows a total amount of work
done as $47,000.00, of which no money has been paid to the
contractor, leaving a balance due of $47,000.00.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN
OF THE CITY OF WICHITA FALLS, TEXAS, THAT:
The repairs and painting of the elevated water tank is
accepted by the City of Wichita Falls, the final estimate is
approved, and the City Manager is directed to pay to the said
contractor the amount due as shown on such estimate.
PASSED AND APPROVED, this 4th day of September, 1979.
MAYOR
ATTEST:
k.1 014 1,67.92‘-d--)
CITY CLERK