Res 2535 5/20/1980RESOLUTION NO.
RESOLUTION APPROVING FINAL PAYMENT AND ACCEPTING
CONSTRUCTION OF MAINTENANCE BUILDING AT KIWANIS
PARK.
WHEREAS, the City of Wichita Falls and T. A. Litteken
Sons, Inc. , as contractor, entered into a contract dated
December 19, 1979, wherein said contractor agreed to construct
a maintenance building at Kiwanis Park; and,
WHEREAS, said construction has been completed in accordance
with the plans and specifications; and
WHEREAS, the total contract price was $25, 084 , of which
22 ,575. 60 has been paid to the contractor, leaving a balance
due of $2 ,508 .40.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN
OF THE CITY OF WICHITA FALLS, TEXAS, THAT:
The construction of the maintenance building at Kiwanis
Park is accepted by the City of Wichita Falls, and the
City Manager is directed to pay to the said contractor the
balance due as shown above.
PASSED AND APPROVED this the 20th day of May, 1980.
M A Y O R
ATTEST:
2
City Clerk