Res 2514 5/6/1980RESOLUTION NO. 445-
1/
4/
RESOLUTION APPROVING FINAL ESTIMATE AND
ACCEPTING CONSTRUCTION OF SANITARY SEWER
MAINS ON JACKSBORO HIGHWAY FROM ARMORY
ROAD TO 30TH STREET
WHEREAS, the City of Wichita Falls and Bowles Construction
Company, as Contractor, entered into a contract dated January 23, 1980,
wherein contractor agreed to construct sanitary sewer mains on Jacksboro
Highway from Armory Road to 30th Street; and,
WHEREAS, said construction has been completed in accordance
with the plans and specifications; and,
WHEREAS, the final estimate has been submitted on this project,
which final estimate shows a total amount of work done as $46,768.40 of
which $44,429.98 has been paid to the contractor, leaving a balance of
2,338.42.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF
THE CITY OF WICHITA FALLS, TEXAS, THAT:
The construction of sanitary sewer mains on Jacksboro Highway
is accepted by the City of Wichita Falls, the final estimate approvedisrovePyyPP
and the City Manager is directed to pay to the said Contractor the amount
due as shown on such estimate.
PASSED AND APPROVED this the 6th day of May, 1980.
C
MAYOR
ATTEST:
City Clerk