Res 2609 8/19/1980RESOLUTION NO. p< dy
RESOLUTION APPROVING FINAL PAYMENT FOR THE PLUM
CREEK DRAINAGE PROJECT.
WHEREAS, the contractor has completed work on the Plum Creek
Drainage Project, and such work has been accepted by the City of
Wichita Falls; and,
WHEREAS, the contract for such work was based on unit prices
for estimated quantities, on this basis, it was originally estimated
that the total cost of the contract would be $208,055.55; and,
WHEREAS, the actual quantities used in the project was less
than the quantities which were originally estimated; therefore, the
total amount of the contract based on the unit prices applied to the
actual quantities is $207. 007.92.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE
CITY OF WICHITA FALLS, THAT:
The total amount due such contractor on the Plum Creek Drainage
Project is $207,007.92, and the City Manager is authorized to make
final payment to such contractor based on this amount.
PASSED AND APPROVED THIS THE 19th day of August , 1980.