Res 2608 8/19/1980RESOLUTION NO. O«P ed(
RESOLUTION APPROVING FINAL PAYMENT FOR THE 1979
STREET RECONSTRUCTION - LIME STABILIZATION PROGRAM.
WHEREAS, the contractor has completed work on the 1979 Street
Reconstruction - Lime Stabilization Program, and such work has been
accepted by the City of Wichita Falls; and,
WHEREAS, the contract for such work was based on unit prices
for estimated quantities; on this basis. it was originally estimated
that the total cost of the contract would be $257,400.00; and,
WHEREAS, the actual quantities used in the project was less
than the quantities which were originally estimated; therefore, the
total amount of the contract based on the unit prices applied to the
actual quantities is $246,701.80.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE
CITY OF WICHITA FALLS, THAT:
The total amount due such contractor on the 1979 Street
Reconstruction - Lime Stabilization Program is $246,701.80, and the
City Manager is authorized to make final payment to such contractor
based on this amount.
PASSED AND APPROVED THIS THE 19th day of August , 1980.
MAYOR
ATTEST:
tj/I 3 c*;c,;vz_,e4a.//
City Clerk