Res 2768 4/7/1981RESOLUTION NO . ("
RESOLUTION APPROVING CHANGE ORDER NO . 1 TO THE
1980 COMMUNITY DEVELOPMENT PAVING PROGRAM
WHEREAS, the City of Wichita Falls and Timmins and Anderson
Corporation, as contractor, entered into a contract dated
May 6, 1980, for the construction of the 1980 Community Development
Paving Program; and,
WHEREAS, Change Order No . 1 in the amount of $93,609. 41 will
increase the estimated contract price to a final value of
1 ,215,714. 61 .
NOW THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF
THE CITY OF WICHITA FALLS, TEXAS, THAT :
Change Order No. 1 to the contract dated May 6, 1980, with
Timmins and Anderson Corporation, a copy of which change order
no. 1 is attached hereto, is hereby approved and the City Manager
is authorized to execute the same for the City of Wichita Falls.
PASSED AND APPROVED this 7th day of April , 1981 .
M A Y O R
ATTEST :
1/..-24-74224•
City Clerk
Page of pages
Agenda Item No.
CONTRACT CHANGE ORDER ORDER NO . 1
DATE : April 7, 1981
CONTRACT FOR : 1980 C. D. Paving Program
OWNER : City of Wichita Falls
TO : Timmins & Anderson Corporation
Wichita Falls, Texas
You are hereby requested to comply with the following changes from
the contract plans and specifications :
DESCRIPTION OF CHANGE INCREASE
1 . Change in contract value due to
changes in quantities of bid items
Third Street} 36,583. 41
2. Change in contract value due to
changes in quantities of bid item
and the addition of items {Mini
Park and Parking Lot at Tenth and
Ohio}57,026.00
Old Contract Price $1,122,105.20
New Contract Price $1 ,215,714.61
See attached payment estimate}
JUSTIFICATION : To facilitate the paving of Third Street from Broad
to Bluff and to provide improvements to the Mini Park
and Parking Lot at Tenth and Ohio.
The amount of the contract will be increased by the sum of Ninety-three
Thousand, Six Hundred and Nine and 41/100 dollars 93,609. 41
Percent increase to the original contract = 8. 34%
This document will become a supplement to the contract and all provisions
will apply hereto.
Requested : {Owner}
Date}
Accepted : {Contractor}
Date}
Page of pages
Agenda Item No.
r
CONTRACT ESTIMATE
PROJECT: 1980 Community Development Paving Program
CONTRACTOR: Timmins & Anderson Corporation
CONTRACT DATE: May 6, 1980
WORKING DAYS: 120
CONTRACT AMOUNT: $1,122,105.20
ITEM UNIT OF PROJECT TOTAL CONTRACT
NO. ITEM MEASURE EST. QUANT. INCREASE QUANTITIES PRICE AMOUNT
1 Standard Curb & Gutter L.F. 24,260 2,122 26,382 5.40 142,462.8
2 2" Type "D" HMAC Surf
Course 4" Asph. Stabilized
Gravel Base S.Y. 33,000 1,903 34,903 15.87 553,910.6
3 Standard Valley Gutter S.F. 4,560 4,600 9,160 4.25 38,930.0
4 4" Concrete Sidewalk S.F. 4,600 400 5,000 3.00 15,000.0
5 Standard Concrete Drive-
way Approach S.F. 4,300 4,300 4.25 18,275.0
6 2" Type "D" HMAC Surface
Overlay on 6" Sandstone S.Y. 16,450 16,450 9.72 159,894.0'
7 2" Type "D" HMAC Surface
Overlay S.Y.300 300 4.00 1,200.01
8 Reinforced Struct. Conc. C.Y. 82.8 44 126.8 475.00 60,230.0
9 Remove and Replace Fence L.F.140 140 6.00 840.0'
10 2" Pipe Hand Rail L.F. 74 74 15.00 1,110.0'
11 Excavation & Placing of
Borrow C.Y. 14,000 14,000 3.68 51,520.0'
12 24" Reinforced Concrete
Pipe L.F. 210 210 38.00 7,980.0
13 30" Reinforced Concrete
Pipe L.F. 96 96 42.00 4,032.01
14 Rip Rap Concrete C.Y. 52 52 200.00 1O,4OO.OI
15 Unclassified Channel
Excavation C.Y.130 130 6.00 780.9'
16 2" Type "D" HMAC on
Limestone Base S.Y. 7,000 7,000 7.80 54,600.0
1? Monolothic Curb L.F. 1,320 1,320 3.50 4,620.0
18 5" Reinf. Concrete Pvt.
on 4" Sandstone S.Y. 2,460 2,460 32.37 79,630.2
ADDITIONAL ITEMS
19 4" Exposed Aggregate Walk S.F. 1,600 1,600 4.75 7,600.0
20 Asphalt Removal S.Y.600 600 4.00 2,400.0
21 Concrete Curb Removal L.F.150 150 2.00 300.0
TOTAL CONTRACT PLUS CHANGE ORDER NO. 1 1,215,714.6
increase to Original Contract = 8.34%