Res 2909 11/17/1981RESOLUTION NO • , /// 1
RESOLUTION APPROVING CHANGE ORDER NO . 1 TO THE
WEEKS STREET ASSESSMENT PAVING PROJECT
WHEREAS, the City of Wichita Falls and Timmins-Anderson
Corporation, as contractor, entered into a contract dated
July 7, 1981 , for the construction of the Weeks Street Assessment
Paving Project; and
WHEREAS, Change Order No. 1 in the amount of $3,651 .68 will
increase the estimated contract price to a final value of
101 ,787. 72•
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF
THE CITY OF WICHITA FALLS, TEXAS, THAT :
Change Order No. 1 to the contract dated July 7, 1981 , with
Timmins-Anderson Corporation, a copy of which Change Order No. 1
is attached hereto, is hereby approved and the City Manager is
authorized to execute the same for the City of Wichita Falls.
PASSED AND APPROVED THIS 17th day of November , 1981 .
M A Y O R
ATTEST :
City Clerk
Page 4 of 4 Pages
Agenda Item No.
CONTRACT CHANGE ORDER ORDER NO. 1
DATE: 11/17/81
CONTRACT FOR: Weeks Street Assessment Paving Project
OWNER: City of Wichita Falls
TO: Timmins - Anderson Corporation
Wichita Falls, Texas
You are hereby requested to comply with the following changes from the contractq
plans and specifications:
DESCRIPTION OF CHANGE AMOUNT
contract value due to changes1. Change in c es9g
in quantities of bid items. increase} $2,439
2. Change in contract value due to changes
in quantities of bid items. increase} $1,740
3. Change in contract value due to change
from Class III 36" R.C.P. to 24" R.C.P. decrease} $527.32
Old Contract Price 98,136.04
New Contract Price 101,787.72
See attached payment estimate}
JUSTIFICATION: To facilitate the future concrete lining of a drainage channel
which drains from the North and East, crossing Weeks Street.
The amount of the contract will be increased by the sum of Three Thousand Six Hundred
Fifty-One and 68/100 dollars 3,651.68.
Percent increase to the original contract = 3.7%
This document will become a supplement to the contract and all provisions will
apply hereto.
Requested: {Owner}
Date}
Accepted: {Contractor}
Date}
Page 2 of 4 Pages
Agenda Item No.