Res 123-82 8/3/1982RESOLUTION NO- /oS J—f Z
RESOLUTION APPROVING CONSTRUCTION AND AUTHORIZING
FINAL PAYMENT TO THE CONTRACTOR ON THE RIGID METAL
FRAME BUILDING AT THE SANITARY LANDFILL .
WHEREAS, the contractor has completed work on the
rigid metal frame building at the Sanitary Landfill in
accordance with the plans and specifications; and,
WHEREAS, the contract for such work was based on
prices for construction submitted in a bid received
April 13, 1982 and awarded by the Board of Aldermen on
May 4 , 1982,
WHEREAS, the project was completed within the
estimated time and within the original bid price; therefore,
the total amount of contract based on the bid submitted
is $28,438. 00.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF
ALDERMEN OF THE CITY OF WICHITA FALLS, THAT :
Such project is hereby accepted by the City of
Wichita Falls- The total amount due such contractor on the
rigid metal frame building at the Sanitary Landfill is
28,438. 001 and the City Manager is authorized to make final
payment to such contractor based on this amount.
PASSED AND APPROVED THIS THE DAY OF uuG cot/ 1982-
M A Y O R
41000000.
ATTEST :
City Clerk
Page 3 of 3 pages
Agenda Item No -