Res 081-82 5/4/1982RESOLUTION NO. /-',a
RESOLUTION APPROVING CHANGE ORDERS NO. 1 AND
NO. 2 TO CONTRACT FOR BELLEVUE PARK IMPROVE-
MENT PROJECT.
WHEREAS, the City of Wichita Falls and C. D. Graham Construc-
tion Company, Inc. , as contractor, entered into a contract dated
March 2 , 1982 , wherein said contractor agreed to construct certain
improvements in Bellevue Park; and,
WHEREAS, it is deemed advisable to execute Change Orders No.
1 and No. 2 , which will increase the contract amount by $2 , 300. 06
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN OF
THE CITY OF WICHITA FALLS, TEXAS, THAT:
Change Orders No. 1 and No. 2 , copies of which are attached
hereto, to the contract with C. D. Graham Construction Company,
Inc. for the construction of Bellevue Park improvements, are
hereby approved, and the City Manager is authorized to execute the
same for the City of Wichita Falls.
PASSED AND APPROVED this the 4th day of May, 1982 .
y7Y 0 R
ATTEST:
City Clerk
v r.
Ak( lilitt I j
ORDER cO•sTRACiOF: pcj
Him Li
A/A DOCUMENT G701 OTFHCF:
PROJECT: Bellevue Park CHANGE ORDER NUMBER: # 1
n: me. address)
TO (Owner)
City of Wichita Falls
ARCHITECT'S PROJECT NO: B7$-79—$0—$1
Parks & Recretion Dept. CONTRACT FOR: MC4$-0030
P. 0. Box 1431
Wichita Falls, Texas 76307
L A CONTRACT •DATE: 3-2—$2
The following changes are:
Jack Peirce Electric (Copy enclosed) 616.72
Plus 20% Overhead & Profit 123.34
740.06
The orig:na' C r nir,'e • ern,211,905•00
t t c i i r
The eonlraet S::m l,ns r to irus ( han,:c Order vac 5 211,905.00
The Contact Sum s. I! He (inc•e,I•ed, WI CcXcXi, Fl) (t.XXX3C.cYai) by this Change Order . . 5 740.06
The new Contract Sum including this Change Order will be 212,645.06
The Contract Time v%ill he POCOC Vii) (unchanged) by Days.
The Date of Completion as of the date of this Change Order therefore is
C.D. Graham Constr. Co.
ARCHITECT C ''
2u
CTuaF. OWNER
cksboro Hwy.
Address Address Address
Wichita Fal , Texas
62
BY BY ( •L--''tom_— 'BY
DATE DATE April 20, 19$2 DATE
e n' rl :r r r • . r . .. . 1 n t ,' '-r
a
JACK,. PEIRCE ELECTRIC
PHONE (817) 322-1812 1901 TENTH STREET, ROOM 112 • WICHITA FALLS, TEXAS 76301
April 9. 1982
C. D. Graham Construction Co. re: Bellevue Park
5202 Jacksboro Hwy
Wichita Falls, Texas 76302
Gentlemen:
We propose to add 2 walk fixtures, 2 weatherproof receptacles and 120V circuit
and stub out at pole *3 or circuit CR6 for the sum of $ 616. 72
Material Price lfabor Price
10 3/4" PVC 22. 27c 2.23 6.00 60
2 3/4" PVC Elbow W/Coup. 79. OOc 1. 58 30.00 60
3 3/4" PVC Adapter 33. OOc 99 7.00 21
1060 ' V10 Copper Wire 69. 52m 73. 69 7. 60m 8.06 _
2 W. P. Duplex Recpt. W/cover 7. 50@ 15. 00 1. 20@ 2.40
2 Walk Lights 56. 00@ 112. 00 1. 50@ 3.00
205. 49 14. 86
Material 205. 49
Labor 14. 86.@ 13.10 194. 67
Labor 3. 72@ 14. 15 52. 64
Labor Fringes 56. 88
509. 68
Plus 10% Overhead 50. 97
Plus 10% Profit 56. 07
Total 616. 72
Thank you „
9
a.
Jack Peirce
JP/ap
CONSTRIICTlnr\l _ IMc -r I I nTln +
6
r r _Ci i.i .`iL AR(.IIi7F(.1 L
O[ DER CO'-1 RACTO ICJ
FIELD I
A!A DOC(JMEN7 C701 OTHER
PROJECT: Bellevue Park CHANGE ORDER NUMBER: # 2
te..me, address)
TO (Owner)
ARCHITECT'S PROJECT NO: B7$-79—$0-$1
City of Wichita Falls MC4$-0030
Parks & Recretion Dept. CONTRACT FOR:
P. 0. Box 1431
Wichita Falls, Texas 76307
L j CONTRACT DATE: 3-2—$2
The following changes are Corner B - Labor and
Material on changing grade and length of ramps
and changing center ramp to 6' width.
1, 560.00
The c'ri,';n, l r_ ; r;trac u;m 5 211,905.00
I r 740.06
The Contra(t :nr I.iir•: to this (_Mange Orricr ..ac 212,645.06
The Contract Sum s',ili he (increaed) (dkENNaXuCh (r3QC1XXiitik by this Change Order . . . $ 1, 560.00
The new Contract Sum including this Change Order will Lc 214,205.06
The Contract Time will he (ikcW41) (dPXal.Q'X(unchanged) by Days.
The Date of Completion as of the date of this Change Order therefore is
C. D. Graham Constr. Co.
ARCHITECT C FCT )R OWNER
dacksboro Hwy.
Address Address Address
Wichita Falls Texas
BY BN'14. BY
DATE DATE April 20, 19$2 DATE
AID p rin. •T (. rr (i. r, . r• it r,