Res 010-82 1/19/1982RESOLUTION NO.
RESOLUTION APPROVING CHANGE ORDER NO. 2
AND ACCEPTING CONSTRUCTION OF RENOVATION
WORK AT WICHITA FALLS MUNICIPAL AIRPORT.
WHEREAS, the City of Wichita Falls and C. D. Graham
Construction Company entered into a contract dated May 6 ,
1981 for renovating portions of the Municipal Airport Ter-
minal Building; and,
WHEREAS , Change Order No. 2 makes certain minor changes
which reduces the total contract sum by $499. 05; and,
WHEREAS, the construction of such project has been com-
pleted in accordance with the plans and specifications; and ,
WHEREAS , the original contract amount was $185 ,316 , which
has been increased by change orders to $189, 944 . 94 . Of this
amount, $170,881. 39 has been paid to the contractor, leaving
a balance due of $19, 063. 55.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF ALDERMEN
OF THE CITY OF WICHITA FALLS , TEXAS , THAT:
Such Change Order No. 2 is hereby approved, and construc-
tion of such project is hereby accepted by the City of Wichita
Falls. The City Manager is authorized to make final payment
to such contractor of the balance due as shown above.
PASSED AND APPROVED THIS the 19th day of January, 1982 .
M A Y O R
ATTEST:
City Clerk