Res 155-83 9/6/1983RESOLUTION NO. 155-83
RESOLUTION APPROVING CHANGE ORDER NO. 3 TO CONTRACT
WITH ELECTRA CONSTRUCTION CO. FOR NORTHSIDE FIRE
STATION NO. 9 , FOR AN ADDITIONAL $1, 535 .65 .
WHEREAS, the City of Wichita Falls and Electra Construction Co.
entered into a contract dated April 5, 1983 for the construction of
the Northside Fire Station No . 9; and,
WHEREAS, Change Order No. 3 to such contract has been proposed,
which would add the installation of concrete sidewalk and six inch
fiberglass batt insulation above the ceilings, which change order
will increase the amount of the contract by $1,535 .65 .
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS, TEXAS, THAT:
That certain Change Order No. 3, a copy of which is attached
hereto, to the contract with Electra Construction Co. for the
construction of such Fire Station No. 9, is hereby approved, and
the City Manager is authorized to execute the same for the City of
Wichita Falls .
PASSED AND APPROVED this the 6th day of September, 1983 .
A Y O R
ATTEST:
City Clerk
t),It,'rrt
83029VI..u."xe' August 2, 198 r hoer t,.l'riii( I 'cr
fn ; change
Three ( ) L r,ti 3 I'rrr,eet Fire Station #9
T?
Order No
Wir i 1 tll_____ 1It U S1I11. X S 1 ,535.65 Address Castle Road
Ardiitl'cts/Platlners
906 Burnett Owner• City of Wichita Falls
Wichita FallsTexa.176301 contractor Electra Construction Co.
7]817/761-2404
TO: The City of Wichita Falls Contract for: $183,419.00
P.O. Box 1431 C.O. #3- $184,954.65
Wichita Falls, Texas 76307 Contract date: April 5,1983 to
Attn. : Chief Jim Jameson
August 15, 1983
CONTRACTOR: Electra Construction Co. - Electra, Texas C.O. #2 - August 25, 1983
1 You are authorized to make the following changes in the Subject Contract:
1. Install 4'-0" wide concrete side walk (4" thick with W1.5 x W1.5 WWF) across the
front of the property from the south property line to the north property line as
per City of Wichita Falls requirements.
1,250.00)
i 2. Install 6" .fiberglass batt insulation above all ceilings which were not already .
specified or indicated on plans for installation of insulation. 285.65)
9
1 -
I The amount of the Contract will be(increased)i4t9G Cl(`3tdd by the Sum of:
One Thousand Five Hundred Thirty-Five and 65/100's ---- oollarst$1535.65
Contract total including this Change Order will be:
One Hundred Eighty-four Thousand Nine Hundred Fifty-four and 65/100' s Dollars
xx
lxgagor,x,x.k.KFx.xatixamomx,x464xx.xixxxx ,
Contractor's Ac ept
ea6-fKf7t/7,,—
ce >
D
Owner's Acceptance: Architect.Recommendation
p[/?' 8y:ti
B. f -^3/—'
By 1
Date. August 4, 1983 Date:
r — i 3 Da(e August 2, 1983
J Bundd,Younc, Suns Page 3 of 3 Pages
Agenda Item No. 8.a.