Res 133-83 7/5/1983I
1 RESOLUTION NO. /V-11
RESOLUTION ACCEPTING CONSTRUCTION AND AUTHORIZING
FINAL PAYMENT TO THE CONTRACTOR FOR THE CONSTRUCTION
OF THE FENCE AT THE SANITARY LANDFILL ON PARKER
ROAD.
WHEREAS , the City of Wichita Falls and A-1 Discount Fence
Company entered into a contract dated May 17 , 1983, for the
construction of a fence at the sanitary landfill on Parker Road;
and,
WHEREAS, said project has been completed in accordance with
the plans and specifications ; and,
WHEREAS , such contract was a unit price contract, and the
estimated cost based on estimated quantities was $11,294 . 10 ; however,
on the basis of the actual quantities used in the construction, the
total contract price is $11, 043 .55 , none of which has been paid to
the contractor.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF WICHITA FALLS , TEXAS , THAT:
The construction of such project is accepted by the City of
Wichita Falls, and the City Manager is authorized and directed to
pay to the contractor the amount due of $11, 043 . 55 .
PASSED AND APPROVED this the 5th day of July, 1983 .
Y O R7A
ATTEST:
47-..L.2-2/)--tie.-- '( /149-fri--zded---
9
Cit Clerk