Res 078-83 4/19/1983RESOLUTION NO. 74475
RESOLUTION APPROVING CHANGE ORDER NO. 1 AND
ACCEPTING CONSTRUCTION OF COLONIAL PARK FLOOD
CONTROL PUMP IMPROVEMENTS .
WHEREAS, the City of Wichita Falls and Onyx Construction Co . , Inc .
entered into a contract dated November 2, 1982, wherein the Contractor
agreed to construct certain Colonial Park flood control pump improve-
ments; and,
WHEREAS , during construction certain unknown existing conditions
were uncovered which required additional construction in order to
make the system function; this additional construction is set out
in Change Order No . 1 , which increases the contract amount by
10 , 870 .00; and,
WHEREAS , the construction has been completed in accordance
with the plans and specifications; and,
WHEREAS, the original contract price for this project was
445, 720 .00, of which $423, 434 .00 has been paid to the Contractor,
leaving a balance due of $22, 286 .00 , plus the $10 , 870 .00 due under
such Change Order No. 1 .
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF WICHITA FALLS , TEXAS , THAT:
Change Order No . 1 is hereby approved, the construction of such
project is hereby accepted by the City of Wichita Falls , and the
City Manager is directed to pay to the said Contractor the balance
due as set out above .
PASSED AND APPROVED this the 19th day of April, 1983 .
1°..."
V
A Y O R
ATTEST:
Ji---,1494,/64t, ,
71-4t-m.,,,d..)
City Clerk