Res 047-86 4/1/1986RESOLUTION NO. /-/Z7--& RESOLUTION APPROVING CHANGE ORDER NO. 2 FOR THE HOLLIDAY CREEK EXCAVATION PROJECT PHASE ONE WHEREAS, the City of Wichita Falls and Zack Burkett Company as contractor, entered into a contract November 19, 1985, wherein said contractor agreed to construct the Holliday Creek Excavation Project Phase One; and, WHEREAS, Change Order No. 2 for the hydromulching from Station 260+00-270+00 of Weeks Park to include surrounding areas disturbed during construction; WHEREAS, this would be an additional $10,500.00 increasing the latest contract value of $1 ,662,449.00 to $1 ,672,949.00. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: Change Order No. 2 in the amount of $10,500.00 would be added for extra construction is approved and the City Manager is authorized to execute Change Order No. 2 for the City of Wichita Falls. PASSED AND APPROVED THIS THE 1ST DAY OF APRIL, 1986. f MI 0 ATTEST: CITY LERK