Res 011-86 1/21/1986RESOLUTION NO. l/--D RESOLUTION APPROVING CHANGE ORDER #1 FOR THE HOLLIDAY CREEK EXCAVATION PROJECT PHASE ONE WHEREAS, the City of Wichita Falls and Zack Burkett Company as contractor, entered into a contract November 19, 1985, wherein said contractor agreed to construct the Holliday Creek Excavation Project Phase One; and, WHEREAS, Change Order #1 for the construction of a pilot channel from stheeastpropertylineoftheCountryClubtoWeeksParkTennis Center, a distance of approximately 8,110 feet and, WHEREAS, this would be an additional $161 ,389.00 increasing the original contract value of $1 ,501 ,060.00 to $1 ,662.449.00. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: Change Order #1 in the amount of $161 ,389.00 would be added for extra construction is approved and the City Manager is authorized to execute Change Order #1 for the City of Wichita Falls. PASSED AND APPROVED THIS THE 21ST DAY OF JANUARY, 1989,7 ATTEST: j CIT CLERK