Res 196-87 11/17/1987RESOLUTION NO. /V--I2
RESOLUTION APPROVING CHANGE ORDER NUMBER 1, ACCEPT-
ING CONSTRUCTION AND AUTHORIZING FINAL PAYMENT TO
THE CONTRACTOR FOR COMPLETION OF THE BUDGET OVERLAY
PROJECT 87-7
WHEREAS, the City of Wichita Falls entered into a contract dated
September 24, 1987 for the construction of the Budget Overlay Project 87-7;
and,
WHEREAS, said project has been completed in accordance with the plans
and specifications, excepting only conditions described in field Change
Order Number 1 for which the Contractor requests an additional $500.00; and,
WHEREAS, said contract was a unit price contract and the cost based on
actual quantities with Change Order Number 1 is $100,904.93; however,
74,699.20 has been paid to the Contractor, leaving a balance due of
26,205.73; and,
WHEREAS, this project was inspected and complete on November 5, 1987.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
WICHITA FALLS, TEXAS, THAT:
The construction of said project is accepted by the City of Wichita
Falls, Change Order Number 1 is approved, and the City Manager is author-
ized and directed to pay the Contractor the amount as set out above.
PASSED AND APPROVED THIS THE 17TH DAY OF i 8 ER, 1987.
i
MAYOR
ATTEST:
i l t 2?/7/ '(W./.1ltA
CIT CLERK