Res 163-87 9/15/1987RESOLUTION NO. /a-60 RESOLUTION TO APPROVE CHANGE ORDER 1 TO CONTRACT FOR REPAIR AND PAINTING OF 0.5 MG NINTH STREET ELEVATED STORAGE TANK AND 0.3 MG JASPER STANDPIPE, ACCEPT THE PROJECT AS COMPLETE, AND AUTHORIZE FINAL PAYMENT WHEREAS, the City of Wichita Falls has a contract with Lupton Painting Company for the painting of the Ninth Street Elevated Water Tank and the Jasper Plant Standpipe; WHEREAS, the original contract cost was $89,900.00 for the painting and repair work; WHEREAS, the City Manager authorized one change order in the amount of 1 ,000.00, bringing the contract cost to $90,900.00; WHEREAS, the work has been completed and the City staff has found said work to be acceptable; WHEREAS, after weather days are allowed, liquidated damages of $90.00 per day are to be assessed for 19 days, a total amount of $1 ,710.00; and, WHEREAS, under the contract the City owes the contractor $9,090.00 less the liquidated damages of $1 ,710.00, an amount of $7,380.00. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: Change Order 1 to the contract is hereby approved in the amount of 1 ,000.00 bringing the total contract price to $90,900.00. The work under the contract is hereby accepted and the City Manager is authorized to ake a final payment of $7,380.00 to the contractor. PASSED AND APPROVED THIS THE 15TH ')A 1 SEPTEMBER, 128 . I MAY O R' ATTEST: CITY ERK