Res 141-88 7/5/1988RESOLUTION NO. 611—&
RESOLUTION TO ACCEPT JASPER STREET WATER
TREATMENT PLANT RENOVATION PROJECT AS
COMPLETE AND AUTHORIZE THE CITY MANAGER TO
MAKE FINAL PAYMENT
WHEREAS, the City of Wichita Falls has a contract with
Decker Construction Company, Incorporated of Abilene, Texas for
renovations at the Jasper Street Water Treatment Plant;
WHEREAS, the original contract in the amount of $403,900.00
was increased by two change orders to $433,000.00;
WHEREAS, previous payments of $404,780.00 have been made,
leaving an amount due of $21,650.00;
WHEREAS, the contract provided for liquidated damages of
$150.00 per calendar day for each additional day beyond 75 days
the upflow clarifier was out of service;
WHEREAS, 30 days of liquidated damages are to be assessed on
this contract, an amount of $4,500.00, leaving a total amount due
to the contractor of $17,150.00; and,
WHEREAS, the City staff has inspected the work and found it
acceptable, and has recommended Council accept this project as
complete.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF WICHITA FALLS, TEXAS, THAT:
The project to renovate the Jasper Street Water Treatment
Plant is accepted and the City Manager is authorized to make a
final payment to Decker Construction Company, Incorporated, in
the amount of $17,150.00.