Res 124-88 6/21/1988RESOLUTION NO. 1A a f RESOLUTION TO ACCEPT PROJECT FOR IMPROVEMENTS TO SEWER LIFT STATION NO. 25 AND AUTHORIZE CITY MANAGER TO MAKE A FINAL PAYMENT TO THE CONTRACTOR WHEREAS, the City of Wichita Falls has a contract with Rhode Pipe Company for certain improvements on Sewer Lift Station No. 25; WHEREAS, the contractor has completed the project and the City staff has inspected the work and found it acceptable; and, WHEREAS, the original contract was for $53,000.00 and previous payments of $51,940.00 have been made, leaving an amount due to the contractor of $1,060.00. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The project to upgrade and improve Sewer Lift Station No. 25 is hereby accepted and the City Manager is authorized to make a final payment to the contractor of $1,060.00. PASSED AND APPROVED THIS THE 21ST DAY OF JUNE, 1988. ATTEST: CITY LERK i o �