Res 123-88 5/31/1988RESOLUTION NO. /J3 -#
RESOLUTION APPROVING CHANGE ORDER #5,
ACCEPTING CONSTRUCTION AND AUTHORIZING FINAL
PAYMENT TO THE CONTRACTOR FOR THE COMPLETION
OF THE PHASE "E" - CONCESSION AND SCORER'S
BUILDING AT THE SOFTBALL COMPLEX
WHEREAS, the City of Wichita Falls entered into a contract
on September 15, 1987, for the construction of Phase "E" -
Concession and Scorer's Building at the City Softball Complex;
and,
WHEREAS, said project has been completed in accordance with
the plans and specifications; and,
WHEREAS, the work has been completed for a cost of
$169,612.43, of which $147,921.93 has previously been paid to the
contractor, leaving a remaining balance of $21,690.50; and,
WHEREAS, the City staff has inspected the work and found it
to be acceptable.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF WICHITA FALLS, TEXAS, THAT:
The Phase "E" - Concession and Scorer's Building project is
hereby accepted, Change Order #5 is approved, and the City
Manager is authorized to make final payment to the contractor in
the amount of $21,690.50.