Res 073-88 4/5/1988RESOLUTION NO. RESOLUTION ACCEPTING THE CONSTRUCTION OF THE LANDFILL SOIL LINER PROJECT III AND AUTHORIZING FINAL PAYMENT TO THE CONTRACTOR WHEREAS, the City of Wichita Falls entered into a unit price contract with B. D. Haynes Company for the construction of the Landfill Soil Liner Project III; and, WHEREAS, the actual cost of said contract was $230,096.40, however, being that $218,591.58 has previously been paid to the contractor and that, further $1,000.00 is rightfully due to the City as liquidated damages as required by the contract leaving an amount due of $10,504.82. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF WICHITA FALLS, TEXAS, THAT: The Landfill Soil Liner Project III is accepted and the City Manager is authorized to make final payment to the contractor in the amount of $10,504.82. PASSED AND APPROVED THIS THE 5TH ATTEST: CITY CLERK